Building control on a London home project: full plans or building notice, inspections, completion certificates and 2026 council fees

Building control checks that an extension, loft or structural change is built safely, and produces the certificate you need when you sell. Here is how the two application routes work, what inspections to expect, what councils charge in 2026 and the warning signs.

· Written by the Web Designer Limited editorial team · Published by Web Designer Limited · About this site

Sunlit timber stud-wall framing with a wooden sole plate, loose offcut boards and a black cable on the floor

Photo by Ron Lach on Pexels.

Building control is the part of a home project that most homeowners never see until something goes wrong. It is the system that checks your extension, loft, structural opening or new bathroom against the Building Regulations, and it produces the certificate your buyer’s solicitor will ask for years later. A builder who “doesn’t bother with all that” is not saving you money. They are passing a legal and financial risk to you.

This guide explains how building control works for a London house, the choice between a full plans application and a building notice, what inspections and certificates to expect, what councils charge in 2026, and the warning signs that a builder is cutting corners.

Planning permission and building control are different

GOV.UK makes the point plainly: building regulations approval is different from planning permission, and you might need both. Planning decides whether a project is acceptable in its setting, such as its size, its look and its effect on neighbours. Building regulations decide whether it is built safely, covering structure, fire safety, drainage, insulation, ventilation and electrics.

Plenty of projects need building regulations approval but no planning permission. GOV.UK lists examples including installing a bathroom that involves plumbing, changing electrics near a bath or shower, replacing windows and doors, replacing roof coverings, and installing or replacing a heating system. Extensions, loft conversions and removing a load-bearing wall are covered too. If you are not sure, GOV.UK advises checking with a building control body.

Who can check your work

For an ordinary house, GOV.UK says you can apply to your local council or to a private registered building control approver. If you choose a private approver, they tell the council about your work by giving an “initial notice”.

All private businesses that carry out building control work in England must be registered with the Building Safety Regulator. Before you or your builder appoint one, look them up on the government’s register of building control approvers. It shows each approver’s name and address, registration number, the type of work they are registered to do, their registration dates and any conditions.

Some work does not need a separate application at all. GOV.UK explains that you do not need to get approval yourself if you use someone registered with a competent person scheme, such as an electrician or a gas or window installer who can self-certify. Our guide to competent person schemes lists the certificates you should receive.

Full plans or building notice

For work that is not on a high-rise residential building, GOV.UK describes two main routes:

  • Full plans. Drawings and details are checked before work starts. GOV.UK says to expect a decision within 5 weeks, or 2 months with your consent, and a completion certificate usually within 8 weeks of the work being finished, as long as it complies.
  • Building notice. Only for smaller projects. Work can start 2 days after the notice is submitted, but there is no formal approval of the plans.

The difference matters if something goes wrong. Under section 36 of the Building Act 1984, a building control authority can serve a notice on the owner requiring work that breaks the regulations to be pulled down or altered. Since the Building Safety Act 2022, such a notice can be given up to 10 years after the work was completed. The same section protects owners who used the full plans route: where an application was approved and the work was carried out in line with the approved plans and any requirements, a section 36 notice cannot be given on the ground that the work breaks the regulations. On a structural project, that protection is a strong reason to choose full plans.

Inspections and the completion certificate

Whichever route you use, a building control surveyor inspects the work at key stages, for example foundations, drainage, steel beams, insulation and the finished job. Ask your builder for the inspection schedule at the start and make sure they book each visit before the work is covered up. If foundations are concreted or a beam is boxed in before it has been seen, it may have to be opened up again at your cost.

At the end you should receive a completion certificate (or a final certificate from a private approver). Do not make the final payment until it is issued or you know exactly what is outstanding. GOV.UK warns that without approval you will not have the certificates of compliance you may need when you sell your home.

What councils charge in 2026

Councils set their own building control charges, based on their costs, and private approvers agree fees directly with you. Two London examples show the scale:

  • Southwark (2026 to 2027 charges): for an extension or loft conversion of less than 40 m², the full plans route costs £589.10 for the plan charge plus £883.65 for inspections, including VAT. A building notice costs £1,472.76 including VAT.
  • Sutton (charging schedule in effect from 7 November 2026): for a single-storey extension under 40 m², the plan charge is £504 and the inspection charge £756, including VAT, for a total of £1,260. A building notice is also £1,260. A regularisation application for the same work, after it has been built without approval, costs £1,575.

The fee is small compared with the cost of the build. If a quote does not say who is paying it, or which building control body will be used, ask before you sign.

If work was done without approval

GOV.UK explains that you can apply to a council, but not a private approver, for “regularisation”, which is retrospective approval for work carried out without consent. Only work carried out after 11 November 1985 can be approved this way, and you may need to open up or alter the work before a regularisation certificate is issued. GOV.UK also warns that the person doing the work could be prosecuted and fined, and that the building control body could make you pay to fix faulty work. As the owner, it is your property that carries the problem when you come to sell.

Red flags from a builder

  • “You don’t need building regs for this” on an extension, loft, structural opening or new bathroom, with no explanation.
  • A builder who will not tell you which building control body they are using, or a private approver you cannot find on the register.
  • Pressure to use a building notice on a large structural job so work can “start Monday”.
  • Foundations, drains or steels covered up before an inspection.
  • No mention of electrical or gas certificates from a competent person scheme.
  • A request for the final payment before the completion certificate. Citizens Advice also suggests a deposit of no more than 25% and paying by credit card where possible.

A short plan that saves time and money

  1. Check whether your project needs planning permission, building regulations approval or both.
  2. Decide who will apply, and whether to use the council or a registered private approver, before you sign the building contract.
  3. For structural work, choose the full plans route and get the plans approved before work starts.
  4. Agree the inspection stages with the builder, and tie stage payments to inspections that have been passed.
  5. Keep the completion certificate, the approved drawings and every competent person certificate with your house papers.

Sources were checked on 23 November 2026. Council charges usually change each year, so check your own borough’s current schedule. For more help, see our guides to vetting a building contractor, comparing building quotes like for like, deposits and staged payments and building over a sewer, our services page and the questions page. If you would like a quote, use the quote form.

Quick answers

Do I need building control if I don’t need planning permission?

Often, yes. Building regulations approval is separate from planning. Extensions, loft conversions, structural openings and many bathroom, window and heating jobs need approval, unless the work is done by a competent person scheme member who can self-certify it.

Is full plans or a building notice better?

For structural work, full plans is usually safer. The plans are checked before work starts, and the Building Act protects owners whose work follows approved plans. A building notice lets work start after 2 days but gives no formal approval and is meant for smaller projects.

What happens if my builder did work without building control?

You can apply to the council for regularisation, which may mean opening up the work. In Sutton this costs £1,575 for a single-storey extension under 40 m². A building control authority can require non-compliant work to be altered or removed for up to 10 years after completion.